SAFETY ADVISORY: ROAD CLOSURE AND ACCESS RESTRICTIONS
Due to severe shoreline erosion, portions of Point Dume Beach remain closed or have restricted access while Los Angeles County conducts emergency shoreline protection and infrastructure repairs.
Current Access Restrictions
- Point Dume Beach access road: Beginning at the intersection of Westward Beach Road and Birdview Avenue is closed to vehicles at all times.
- Pedestrian and cyclist access: Pedestrians and cyclists are prohibited from entering active construction areas. Construction generally takes place from 5 a.m. to 3 p.m.
- Restrooms 1, 2 and 3: Closed due to damage to the water service. Temporary toilets and handwashing stations are available.
Emergency Repair Update
The County continues working to protect public access, beach facilities and infrastructure damaged or threatened by coastal erosion. While some shoreline protection work is complete, additional repairs are underway or planned.
For information about completed work, ongoing repairs and anticipated timelines, visit the Emergency Erosion Repairs tab.
Last updated: October 30, 2026.
Point Dume has over one mile of ocean frontage with 34 acres of sand. It is surrounded by headlands, cliffs, rocky coves, and vast beach access.
Amenities include restrooms, showers, restaurants, 373 parking spaces, and a hiking trail. Popular activities include swimming, diving, surfing, and scuba diving. The hiking trail leads to an ancient coastal bluff sand dune.
On a clear day visitors can enjoy an incredible view encompassing the entire Santa Monica Bay and distant Catalina Island.

POINT DUME BEACH SURF REPORT
Rotate Phone to View

EMERGENCY EROSION REPAIRS
Last updated: October 30, 2026.
Overview
Severe shoreline erosion has damaged the access road between the Westward Beach Road/Birdview Avenue intersection and the Point Dume Beach parking lot, as well as water infrastructure serving public beach facilities. Continued erosion has also threatened existing shoreline protection, public restrooms and lifeguard facilities.
In response, the Los Angeles County Department of Beaches and Harbors (DBH) has undertaken emergency shoreline protection work along the access road and at Point Dume Beach. This includes installing new rock revetments and repairing existing ones to help stabilize vulnerable areas and protect public infrastructure. At the City of Malibu’s request, the County also installed additional shoreline protection near Birdview Avenue to protect the City’s right-of-way.
DBH continues to monitor shoreline conditions and coordinate emergency repairs with the City of Malibu, Los Angeles County Public Works and relevant regulatory agencies while preparing for the upcoming winter storm season.

Point Dume Beach Access Road: Emergency Shoreline Repair Work Areas (1-4) – October 12, 2026
Emergency Repair Timeline and Next Steps
Completed Work
- July 31–August 1, 2026 | Erosion Damage and Closures
Severe shoreline erosion damaged the beach access road and water infrastructure serving public restrooms, prompting closures. - August 5–13, 2026 | Initial Shoreline Protection
In Area 1, contractors installed approximately 235 feet of emergency rock revetment to protect the beach access road. - August 2026 | Water Infrastructure Replacement
Los Angeles County Public Works Waterworks District 29 installed a replacement water main and meter. - September 8–October 23, 2026 | Additional Shoreline Protection
In Area 2, contractors installed approximately 230 feet of new rock revetment to protect the beach access road. Of that total, 120 feet was installed at the City of Malibu’s request to protect its right-of-way near the Westward Beach Road/Birdview Avenue intersection. In Area 3, contractors repaired approximately 230 feet of existing rock revetment.
Current and Upcoming Work
- October 26, 2026 | Beach Facility Protection Begins
Emergency shoreline protection work began near the Point Dume lifeguard building and two public restroom facilities. This work will be ongoing. - Upcoming | Existing Shoreline Protection Repairs
In Area 4, emergency repairs are planned for approximately 325 feet of existing rock revetment along the beach access road. - Upcoming | Water Service Restoration
DBH is coordinating the remaining water line installation and reconnection to restore service to affected public restrooms. - Upcoming | Roadway Repairs
Engineers are developing plans for repairs to the beach access road and improvements to stormwater drainage.

Shoreline Erosion Near Pointe Dume Lifeguard Station – October 12, 2026
Regulatory Authorization and Agency Coordination
Emergency shoreline protection work completed or underway to date was authorized by the California Coastal Commission and the City of Malibu. As shoreline conditions evolve and additional repairs are identified, DBH continues to coordinate with regulatory agencies regarding any additional required authorizations.
DBH is also working with the City of Malibu to protect the Westward Beach Road/Birdview Avenue intersection and with Los Angeles County Public Works Waterworks District 29 to restore damaged water infrastructure.
Public Access and Safety
Portions of Point Dume Beach and the beach access road remain restricted while emergency repairs continue. Visitors should observe posted closures and avoid active construction areas. For current vehicle access, pedestrian and cyclist restrictions, and restroom availability, refer to the Safety Advisory on the Overview tab.
Project Updates
The County will update this page as additional construction milestones, repair schedules and public access information are confirmed.